Cycle Steward · independent PSAP workspace
Cycle Steward Portal
All guides

Not a residual project

Stand up a new PSAP

A new answering point is a connectivity / plan action (TD-280 family), not leftover CPE money. County Coordinator, network, MSAG/GIS, and Branch planning all have to exist before anyone shops workstations.

Plan 12–24 months. Do not promise a go-live from a vendor slide.

Flow

  1. 01

    Need & authority

    City/county resolution, 9-1-1 jurisdiction, why a new PSAP vs host-remote.

  2. 02

    County Coordinator

    MSAG, default routing, neighboring PSAP impact. This is not optional.

  3. 03

    TD-280 family

    New PSAP / plan / connectivity variants — not a CPE residual form.

  4. 04

    Network path

    How calls will arrive (legacy or NG). Separate from CPE allotment.

  5. 05

    CPE vehicle

    Once the PSAP exists, CPE follows Chapter III on the active MPA — new identity, new letter.

  6. 06

    GIS / ALI

    Location data ready before first live call. Different pot from CPE residual.

  7. 07

    Go-live & FOR

    Test calls, answer-time watch, then the first Fiscal & Operational Review.

Checklist

0 of 9 complete

Required documents

  • TD-280 family
  • Local resolution / authority
  • Network order
  • CPE Advanced Notification (new identity)
  • GIS/MSAG plan
  • STD-204

Common mistakes

  • Shopping CPE first

    Workstations without a network path and a PSAP identity bounce.

  • Charging stand-up to someone else’s residual

    Residual belongs to a complete funded system at that PSAP.

  • Skipping the County Coordinator

    Default routing and MSAG errors become 9-1-1 errors.