Two tracks, one cutover
Coordinate CPE with NG9-1-1 migration
CPE money does not buy network. Network money does not buy CPE. A refresh that lands in a migrating ESInet window still needs a joint kickoff so 9-1-1 does not drop.
Align CPE install clock with regional NG milestones
Flow
01 →
Name the tracks
CPE = call handling (MPA). Network = ESInet / NGCS (separate contracts).
02 →
Read regional status
Bridge vs migrating vs i3-live changes the coordination load.
03 →
Pick one CPE model
Cloud or on-prem — not both at one PSAP. Both must be i3-capable.
04 →
SOW language
Cite NENA i3 + Cal OES ICD. CAMA→i3 conversion at migration at no added State cost.
05 →
Joint kickoff
PSAP + CPE vendor + network provider + Advisor.
06 →
Facility
Power, HVAC, NG demarc. Site mods are typically PSAP-funded.
07
Cutover plan
Fallback, test calls, answer-time watch, outage SOP.
Checklist
0 of 8 complete
Required documents
- CPE SOW
- Network order / provider record
- NG readiness guide
- Cutover runbook
- Chapter II / XI as needed
Common mistakes
'Our network upgrade uses CPE money'
Usually false. Different contracts and pots.
Skipping the network provider
Install day is too late for a first introduction.
Deploying cloud and on-prem together
New SOW does not allow both at one PSAP.